Before the geomembrane is laid on the slope, the laying area should be inspected and measured. According to the measured size, the anti-seepage membrane with matching size in the warehouse should be transported to the anchorage ditch platform of the first phase. According to the actual conditions of the site, the convenient way of “pushing and laying” from top to bottom should be adopted. The sector area should be cut reasonably so that both the upper and lower ends are firmly anchored. HDPE Control of laying the anti-seepage membrane at the bottom of the field: Before laying the anti-seepage membrane, first transport the anti-seepage membrane to the corresponding position: laying HDPE Control of anti-seepage membrane lamination: Use sand bags to align and align the HDPE The anti-seepage membrane is pressed and pulled by the wind. Laying control in the anchorage trench: At the top of the anchorage trench, a certain amount of anti-seepage geomembrane should be reserved according to the design requirements to prepare for local subsidence and stretching.